DISCHARGING CARGO

Browse By

System described basis my present vessel

FULL DISCHARGE

The following factors are to be considered prior to a full discharge:

•    Maximum available draught at the berth

•    Maximum allowable freeboard on the berth

•    Grade segregation, if carrying multiple grades

•    Crude oil washing requirements

•    Heavy weather ballast requirements

•    Maintenance of satisfactory trim and stress

•    Ballasting operations

When preparing the system to discharge cargo, it is important that all valves are in the closed position prior to setting the lines for discharge and all tank IG connections are set up as required.

a)     All COW valves are to be closed.

b)     Ensure that all overboard valves are closed and sealed and any elbow pieces are removed and spectacle blanks turned to the closed position.

c)     The cargo pumping system and the IG plant is to be prepared for operation.

d)     Open the main lines from the COTs to the main cargo pumps and then up to the manifolds.

e)     Start the IG plant.

f)      Open one set of COTs to each cargo oil pump (COP) and prime the separators.

g)     Open the manifold valves that the discharge arms are connected to.

h)     Start each COP and run at minimum speed, watching the back pressures carefully.

i)       When pumps and pressures are balanced, debottom all tanks by at least 1m in preparation for crude oil washing. If it is intended that the slop tanks are to be used for crude oil washing, they should be discharged and refilled with fresh ‘dry’ crude oil.

j)       Increase to full speed discharge as per the discharge plan and in agreement with the shore installation.

Note: During draining it may be necessary to reduce the speed of the cargo pump on the draining phase and closing in on its pneumatic controlled discharge valve, thereby increasing the back pressure and improving draining performance.

k)     The ballast crossover line to the bottom cargo line is normally kept closed and blanked. The elbow bend between the cargo oil and ballast systems must be removed and the lines blanked.

l)      The crossover  valves between the cargo lines in No.2 and 3 cargo oil tanks can be opened to optimise COP performance, but care must be exercised. Top lines are normally kept isolated to improve draining performance.

m)   When a cargo oil tank reaches  a sounding  of approximately 1.5m, the AUS vacuum pump system can be started and the automatic unloading system activated.

n)     The bottom COW can be started as required when the selected tanks are drained.

o)     Upon completion of discharge, the cargo lines must be drained to the shore tanks.

Procedure for Line Draining

This can be achieved by draining all lines with the stripping pump and pumping the drainings ashore via the MARPOL line. During draining of the lines, the vacuum in the cargo lines must be broken via vacuum breaker valve 228VCD,229VCD and crossover valves 207VCD, 208VCD, 209VCD. The drainings are discharged via the MARPOL line either directly ashore using the MARPOL line manifold valves or via one or more of the cargo manifold lines.

a)    Set the MARPOL line valves for draining ashore via No.1 manifold.

PositionDescriptionValve
OpenMARPOL line block valves port or starboard211VCP 219VCP or 210VCP 218VCP
OpenNo.1 manifold drain valve port or starboard213VCD or 212VCD

b)     Set the pump room valves for draining the lines.

PositionDescriptionValve
OpenNo.1 top line block valve263VCD
OpenNo.2 top line block valve264VCD
OpenNo.3 top line block valve265VCD
OpenNo.1 cargo oil pump discharge valve004VCP
OpenNo.2 cargo oil pump discharge valve009VCP
OpenNo.3 cargo oil pump discharge valve014VCP
OpenNo.1 discharge pneumatic control valveM01VCP
OpenNo.2 discharge pneumatic control valveM02VCP
OpenNo.3 discharge pneumatic control valveM03VCP
OpenStripping pump connection to No.1 COP042VCP
OpenStripping pump connection to No.2 COP043VCP
OpenStripping pump connection to No.3 COP045VCP
OpenStripping pump connection to No.1 COP and strainer049VCP 052VCP
OpenStripping pump connection to No.2 COP and strainer050VCP 053VCP
OpenStripping pump connection to No.3 COP and strainer051VCP 054VCP
OpenStripping pump valves to COP drain line080VCP 081VCP 082VCP
OpenStripping pump suction valve064VCP
OpenStripping pump discharge to MARPOL line067VCP

c)     Start the stripping pump and observe the vacuum on the line.

Listen to the flow at the manifold. Open the vacuum breaking valves as required.

PositionDescriptionValve
OpenVacuum breaker valves to No.4 COT228VCD 229VCD
OpenCrossover  valves  from  vacuum  breaker  to No.1, 2 and 3 top lines207VCD 208VCD 209VCD

d)     On completion of line draining close all valves and agree ship/shore figures.

Segregated ballast loading should be started once bulk discharge has commenced  and  in  accordance with  the  chief  officer’s  unloading  plan, consistent with maintaining the trim and stress within acceptable limits.

FULL  DISCHARGE  OF  A  SINGLE   GRADE   CARGO WITH  COW  OF  BOTH  SLOP  TANKS,  NO.2  AND NO.4 COTS

The following factors are to be considered prior to a full cargo discharge:

•    Maximum available draught at the berth

•    Maximum allowable freeboard on the berth

•    Grade segregation, if carrying multiple grades

•    Crude oil washing requirements

•    Heavy weather ballast requirements

•    Maintenance of satisfactory trim and stress

•    Ballasting operations

When preparing the system to discharge cargo, it is important that all valves are in the closed position prior to setting the lines for discharge and all tank IG connections are set up as required.

a)     Initially all the cargo valves should be shut. The engineering department will carry out the initial preparation work for the running of the IG system and make preparations for warming through the cargo oil pumps (COP). Set up the cargo system and tanks ready to commence discharge of cargo using in this scenario, all three cargo pumps after the initial line clearance.

PositionDescriptionValve
OpenDeck isolating valve and start IG system902VIG
OpenForward crossover valves109VCT 133VCT 110VCT 134VCT
OpenPump room bulkhead master block valves001VCP 006VCP 011VCP
OpenPump room intermediate block valves002VCP 007VCP 012VCP
OpenNo.1, 2 and 3 COP suction valves003VCP 008VCP 013VCP
OpenNo.4 COT suction valves107VCT 115VCT
ClosedNo.1,  2  and  3  COP  pneumatic  controlled discharge valve to top lineM01VCP M02VCP M03VCP
PositionDescriptionValve
OpenNo.1, 2 and 3 COP discharge valves004VCP 009VCP 014VCP
OpenTop line block valves263VCD 264VCD 265VCD

b)     Prime the COP separators, if necessary use the AUS vacuum pumps. The float valve inside each separator should stop any carryover from the cargo tanks into the AUS vapour line.

c)     When  the  shore  terminal  confirm  they  are  ready  to  receive cargo.

PositionDescriptionValve
OpenManifold valves that the discharge valves are connected to202VCD 204VCD 206VCD if port side OR 201VCD 203VCD 205VCD if starboard side

If the loading arms are not connected to all manifolds, then the discharge lines can be made common at the manifold crossover by opening valves 207VCD,208VCD and 209VCD.

During the initial line clearance phase, it will not be necessary to start all three COPs at the same time if all of the manifold connections are not being used. In this scenario with only two lines from ashore, only No.1 and 2 COPs will be used to carry out the testing and security check of the lines and the initial line clearance, No.3 COP will be brought one line when bulk discharge is ready to commence.

d)     Start No.1 and No.2 COPs . As the pump(s) speed is brought up to minimum rpm by the duty engineer, observe that the pump discharge pressure does not rise above 0.5MPa. If necessary open the COPs pneumatic control discharge valve to control the pressure. Open a drop valve on the discharge header if a manifold valve is not yet open.

e)     Commence  the  discharge  line  clearance  at  minimum  speed, carrying out all safety and integrity checks after each pump is started. Close the drop valve if one had been opened.

f)      Debottom all tanks by at least 1m to remove any wet crude once the system has been proved.

g)     Once  the  system   has  been  proved,   and  with  the  shore installation’s agreement, increase the pump speed until the maximum  permitted  back  pressure  or flow  rate  is achieved. Start the third COP as necessary in order to obtain the maximum allowable output. Close in on the appropriate tanks in order to create the stagger according to the chief officers unloading plan. In this scenario the stagger is No.1, 4, 2, 5, 3, 6 and both slop tanks.

h)     As the slop tanks approach the ullage for top washing, set up the fixed tank cleaning machines at the correct angles (130° to 40°) taking drive from No.1 COT and pump. Continue discharging the slop tanks to the draining level with the COPs. Close in on No.1 COP discharge to the top line to maintain at least 0.8MPa on the COW line.

PositionDescriptionValve
OpenNo.1 COP discharge valve to the COW line016VCP 015VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenSlop tanks fixed tank washing machine valves016VTC 039VTC 040VTC
Close InNo.1 COP discharge to top line to maintain 0.8MPa on the COW main004VCP

i)      After top COW of the slop tanks is finished, return No.1 COP to continue discharging the slop tanks to their draining level, the automatic unloading system should be set up, also reduce the speed of No.2 and No.3 COPs for draining.

PositionDescriptionValve
OpenNo.1 COP discharge valve004VCP
CloseNo.1 COP discharge valve to the COW line016VCP 015VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseSlop tanks fixed tank washing machine valves016VTC 039VTC 040VTC

j)     Prepare to carry out the bottom COW of both slop tanks (40° to 0°).

k)     Warm through the stripping pump, the pump will be used to maintain the slop tanks in a dry condition during bottom COW of both slop tanks, discharging  via the MARPOL line to the manifold. Drive for the COW machines will be from No.1 COT and via No.1 COP.

l)     With the cargo stripping pump ready for operation:

PositionDescriptionValve
OpenStripping pump suction valve064VCP
OpenStripping pump suction valves from the slop tanks030VCP 033VCP
OpenStripping  pump  discharge  to  the  MARPOL line067VCP
OpenMARPOL line to block valves to manifold, (port manifold in use)211VCD 219VCP
OpenMARPOL line to outboard on No.1 manifold valve213VCD
ClosePort  and  starboard  slop  tank  main  suction valves128VCT 127VCT

m)   Commence bottom COW of both slop tanks, closing in on the discharge  valve  from No.1 COP to maintain  0.8MPa  on the COW main.

PositionDescriptionValve
OpenNo.1 COP discharge valve to the COW line016VCP 015VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenSlop tanks fixed tank washing machine valves016VTC 039VTC 040VTC
Close InNo.1 COP discharge to top line to maintain 0.8MPa on the COW main004VCP

n)     On completion of COW and draining of the slop tanks, change over No.1 COP to No.1 COT and No.2 COP to No.2 COT. Return No.3 COP to discharging ashore from No.4 COT. Stop the stripping pump and close the line valves

PositionDescriptionValve
CloseNo.1 COP discharge valves to COW line016VCP 015VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
PositionDescriptionValve
CloseFixed tank washing machine valves016VTC 039VTC 040VTC
CloseSlop tank suction valves127VCT 128VCT
OpenNo.1 COP discharge valve to top line004VCP
OpenNo.1 COT suction valves101VCT 103VCT
OpenNo.2 COT suction valves105VCT 107VCT
OpenNo.4 COT suction valves115VCT 117VCT
CloseStripping pump suction valve064VCP
CloseStripping pump suction valves from the slop tanks030VCP 033VCP
CloseStripping  pump  discharge  to  the  MARPOL line067VCP
CloseMARPOL line to block valves to manifold, (port manifold in use)211VCD 219VCP
CloseMARPOL line to outboard on No.1 manifold valve213VCD

During the bottom COW, ensure that the vessel is trimmed by the stern to facilitate stripping, approximately 3 to 4m. Terminal restrictions may restrict the maximum trim; in addition the vessel’s stability, stress and freeboard must be maintained within the permitted levels. Note the cargo tank suction valves are in wells aligned to the port side of the tanks.

Continue to discharge ashore all other bulk cargo using the maximum number of cargo pumps.

o)     Refill the slop tanks with clean cargo to approximately  50% ullage, sufficient to cover the levelling line. Slowly open the slop tank main suctions and run in fresh crude, as necessary reducing the speed of No.1 and 3 COPs to allow the level to rise.

PositionDescriptionValve
OpenSlop tank main suction valves127VCT 128VCT

p)     On completion of recharging, shut the slop tank main suction valves and increase No.1 and No.3 COP to maximum. If sufficient ullage has not been attained in slop tanks, additional crude can be bled off to the slop tanks via the COP discharge to the eductor.

PositionDescriptionValve
CloseSlop tank main suction valves127VCT 128VCT

q)     When No.4 COTs reach the top wash ullage (COW angle  130° to 70°), set up No.1 COP to supply crude from No.1 COT via the COW line to the fixed tank cleaning machines. Maintain a pressure 0.8MPa on the COW main, closing in on the pump discharge valve to deck as required.

PositionDescriptionValve
OpenNo.1 COP discharge valve to the COW line015VCP 016VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenFixed tank washing machine valves on No.4 COTs013VTC 031VTC 032VTC 030VTC
Close InNo.1 COP discharge valve to the top line004VCP

r)     When top COW of No.4 COTs is complete, continue discharging No.4 COTs to the draining level.

PositionDescriptionValve
CloseNo.1 COP discharge valve to the COW line015VCP 016VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseFixed tank washing machine valves on No.4 COTs013VTC 031VTC 032VTC 030VTC
OpenNo.1 COP discharge valve to the top line004VCP

s)      When No.2 COTs reach the top wash ullage (COW angle  130° to 70°), set up No.2 COP to supply crude from No.4 COT via the COW line to the fixed tank cleaning machines. Maintain a pressure 0.8MPa on the COW main, closing in on the pump discharge valve to deck as required.

PositionDescriptionValve
OpenNo.2 COP discharge valve to the COW line017VCP 027VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
PositionDescriptionValve
OpenFixed tank washing machine valves on No.2 COTs011VTC 025VTC 026VTC 024VTC
Close InNo.2 COP discharge valve to the top line009VCP

t)   When top COW of No.2 COTs is complete, continue discharging No.2 COTs to the draining level.

PositionDescriptionValve
CloseNo.2 COP discharge valve to the COW line017VCP 027VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseFixed tank washing machine valves on No.4 COTs011VTC 025VTC 026VTC 024VTC
OpenNo.2 COP discharge valve to the top line009VCP

u)     As the first set of COTs in the stagger, No.1 and 4 approach the draining level, close the forward crossover valves 133VCT and 109VCT.  Continue  discharging  No.2, 3, 5 and 6 COTs from No.2 and 3 COPs which are still cross connected via forward crossover valves 134VCT and 110VCT.

v)     At the draining level for No.1 and 4 COTs set the AUS system into automatic operation. Strip out both tanks, close the main suction valves on both tank, leaving the stripping suction valve on each tank open.

PositionDescriptionValve
CloseForward crossover valves in No.2 COT133VCT 109VCT
CloseNo.1 and 4 COT main suction valves103VCT 101VCT 117VCT 115VCT
OpenNo.1 and 4 COT stripping suction valves104VCT 102VCT 118VCT 116VCT
OpenNo.2 COP discharge valve to the top line009VCP

w)    On completion of stripping of No.1 COTs, and with a manual dip  indicating  they  are  empty,  close  the  stripping  suction valves. Continue stripping No.4 COTs and prepare to carry out a bottom COW of the No.4 COTs when they are stripped out. Suction for COW is taken from the starboard slop tank via No.1COP. Stripping will be via the stripping eductor returning to the starboard slop tank. Reduce the speed of No.1 COP during the transfer from suction from No.4 COTs to the starboard slop tank.

x)     Set up No.1 COP to provide drive fluid to the tank cleaning machines for No.4 COT and shut No.1 discharge valve to the top line to maintain at least 0.8MPa on the COW line.

PositionDescriptionValve
CloseNo.1 COT stripping suction valves104VCT 102VCT
OpenNo.4 COT stripping suction valves118VCT 117VCT
OpenNo.1  COP suction  from  the  starboard  slop tank032VCP 037VCP 034VCP
CloseNo.1 bottom suction block valve002VCP
OpenEductor  drive  inlet  and  outlet  valve  and discharge to starboard slop tank020VCP 022VCP 031VCP
OpenNo.1 COP discharge valves to COW line015VCP 016VCP
CloseNo.1 COP discharge to the top line004VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
Open SlowlyFixed tank washing machine valves on No.4 COTs013VTC 031VTC 032VTC 030VTC
OpenEductor suction from No.1 bottom line063VCP 060VCP 073VCP

y)     Bottom wash and drain No.4 COTs, as necessary shutting and opening  the stripping  suction  valve on the starboard  tank in order that suction will not be lost with a resultant accumulation of cargo oil in the port tank. This is due to half of the flow into the starboard tank from the COW machines as compared to the port tank.

z)     On completion of bottom COW, reduce the speed on No.1 COP and change over to discharge the starboard slop tank to shore from the main suction,  close all valves  to the tank cleaning machines.

PositionDescriptionValve
OpenNo.1 COP discharge valve to the top line004VCP
CloseNo.1 COP discharge valve to the COW line015VCP 016VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenSlop  tank  main  suction  valve  and  bottom block valve127VCT 002VCP
CloseNo.1 COP stripping suction valves from the starboard slop tank032VCP 037VCP 034VCP
CloseEductor suction from No.1 bottom line063VCP 060VCP 073VCP
CloseEductor  drive  inlet  and  outlet  valve  and discharge to starboard slop tank020VCP 022VCP 031VCP

aa)   On completion of stripping the starboard slop tank, No.1 COP can be shut down.

Shutting down No.1 COP should coincide with the stagger in the discharge, whereby No.2 and 5 COTs should be approaching  their stripping stage. At this point the forward crossover valves 110VCP and 134VCP should be shut, allowing No.2 pump to strip No.2 and 5 COTs and conduct a COW of No.2 COTs. No.3 COP will continue on bulk discharge from No.3 and 6 COTs.

bb)   When No.5 COTs reach their stripping stage, close the main suctions on No.2 and 5 and leave the stripping suctions open. Shut the stripping suctions on No.5 COT when they are dry and the manual dip confirms they are empty. Continue stripping No.2 COTs down to the level where they are almost dry, then set up for the bottom COW of these tanks via No.2 COP, taking the drive for the COW machines and eductor from the port slop tank.

CloseNo.2 COP stripping suction valves from the port slop tank029VCP 038VCP 035VCP
CloseEductor drive inlet, outlet and discharge to the port slop tank020VCP 022VCP 023VCP 024VCP

ee)   On completion of stripping the port slop tank No.2 COP can be shut down.

Shutting down No.2 COP should coincide with the stagger in the discharge, whereby  No.3  and  6  COTs  should  be  approaching  their  stripping  stage. Continue discharging these tanks down to their stripping level, shutting the main suctions valves and leaving the stripping valves open.

PositionDescriptionValve
CloseNo.3 and 6 COT main suction valves113VCT 111VCT 125VCT 123VCT
OpenNo.3 and 6 COT stripping suction valves114VCT 112VCT 126VCT 124VCT
PositionDescriptionValve
CloseNo.5 COT stripping suction valves122VCT 120VCT
OpenNo.2 COT stripping suction valves108VCT 106VCT
OpenNo.2 COP suction from the port slop tank029VCP 038VCP 035VCP
CloseNo.2 bottom suction block valve007VCP
OpenEductor  drive  inlet  and  outlet  valve  and discharge to port slop tank020VCP 022VCP 023VCP 024VCP
OpenNo.2 COP discharge valves to COW line017VCP 027VCP
CloseNo.2 COP discharge to the top line009VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
Open SlowlyFixed tank washing machine valves on No.2 COTs011VTC 025VTC 026VTC 024VTC
OpenEductor suction from No.2 bottom line063VCP 061VCP 074VCP

cc)   Bottom wash and drain No.2 COTs, as necessary shutting and opening  the stripping  suction  valve on the starboard  tank in order that suction will not be lost with a resultant accumulation of cargo oil in the port tank. This is due to half of the flow into the starboard tank from the COW machines as compared to the port tank.

dd)   On completion of bottom COW, reduce the speed on No.2 COP and change over to discharge the port slop tank to shore from the main suction, close all valves to the tank cleaning machines.

PositionDescriptionValve
OpenNo.2 COP discharge valve to the top line009VCP
CloseNo.2 COP discharge valve to the COW line017VCP 027VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenPort slop tank main suction valve and bottom block valve128VCT 007VCP
CloseNo.2 COP stripping suction valves from the port slop tank029VCP 038VCP 035VCP
CloseEductor drive inlet, outlet and discharge to the port slop tank020VCP 022VCP 023VCP 024VCP

ee)   On completion of stripping the port slop tank No.2 COP can be shut down.

Shutting down No.2 COP should coincide with the stagger in the discharge, whereby  No.3  and  6  COTs  should  be  approaching  their  stripping  stage. Continue discharging these tanks down to their stripping level, shutting the main suctions valves and leaving the stripping valves open.

PositionDescriptionValve
CloseNo.3 and 6 COT main suction valves113VCT 111VCT 125VCT 123VCT
OpenNo.3 and 6 COT stripping suction valves114VCT 112VCT 126VCT 124VCT

ff)    On completion of final draining in No.3 and No.6 COTs and when a manual dip confirms  that they are empty, stop No.3 COP.

The vessel is now ready to carry out draining of all lines as explained earlier in the blog. .

gg)   Drain the lines and pumps using the stripping pump, discharging up  the  MARPOL  line  to the  appropriate  shore  hose.

hh)   On completion of line draining, close all valves and agree ship/shore figures.

Segregated  ballast loading should be started as stated in the chief officer’s discharging plan, consistent with maintaining the trim and stress within acceptable limits.

After the final figures have been agreed, final adjustment to the ballasting can now be carried out in order to bring the ship into the required departure trim condition.

DISCHARGING   A   THREE   GRADE    CARGO   WITH 100% COW, PIPELINE  ADMIXTURE AND ONE VALVE SEPARATION ACCEPTABLE

Prior to arrival at the discharge port, a cargo plan shall be completed covering all aspects of the proposed discharging  operation. This will ensure that the stability, stress, draught and trim are all within acceptable levels throughout the discharge, and comply at all times with terminal restrictions.

The following factors are to be considered prior to discharge:

•    Maximum available draught at the berth

•    Maximum allowable freeboard on the berth

•    Grade segregation

•    Crude oil washing requirements

•    Heavy weather ballast requirements

•    Maintenance of satisfactory trim and stress

•    Ballasting operations

When preparing the system to discharge cargo, it is important that all valves are in the closed position prior to setting the lines for discharge and all tank IG connections are set up as required.

In the following case example it is assumed that the parcels are segragated as follows:

Group 1

No.1, 4 COT and the starboard slop tank

Group 2

No.2, 5 COT and the port slop tank

Group 3

No.3 and 6 COT

Ship/shore safety checklists must be completed prior to starting cargo discharge. Additionally, the cargo system valve line up should be double checked before commencing the discharge.

a)     Initially all the cargo valves should be shut. The engineering department will carry out the initial preparation work for the running of the IG system and make preparations for warming through the cargo oil pumps (COP). Set up the cargo system and tanks ready to commence discharge of cargo. The intention is to discharge the port slop tank with No.2 COP and line, No.3 COT with No.1 COP and line and the starboard slop tank using No.1 COP and line.

Segregated ballast loading should be started in accordance with the chief officer’s  discharging  plan,  consistent  with  maintaining  the  trim  and  stress within acceptable limits.

PositionDescriptionValve
OpenDeck isolating valve and start IG system902VIG
OpenPump room bulkhead master valves001VCP 006VCP 011VCP
OpenPump room intermediate block valves002VCP 007VCP 012VCP
OpenCOP suction valves003VCP 008VCP 013VCP
OpenCOP discharge valves to top lineM01VCP M02VCP M03VCP
OpenPumproom top line isolating valves004VCP 009VCP 014VCP
OpenTop line block valves263VCD 264VCD 265VCD
OpenNo.3 COTs suction valves111VCT 113VCT
OpenBoth slop tank suction valves127VCT 128VCT

b)     When the shore terminal confirm they are ready to receive cargo open the manifolds the lines are connected to, then start each COP.

PositionDescriptionValve
OpenManifold valves that the discharge hoses are connected to202VCD 204VCD 206VCD if port side or 201VCD 203VCD 205VCD if starboard side

c)     Commence the discharge at minimum speed, carrying out all safety and integrity checks after each pump is started, then debottom all tanks by at least 1m to remove any wet crude once the system has been proved.

d)     Once  the  system   has  been  proved,   and  with  the  shore installation’s agreement, increase the pump speed until the maximum agreed back pressure or flow rate is achieved.

e)     Both slop tanks should be discharged directly to draining level.

PositionDescriptionValve
CloseSlop tank main suction valves127VCT 128VCT
OpenNo.1 COT suction valves101VCT 103VCT
OpenNo.5 COT suction valves119VCT 121VCT
OpenNo.2 COP discharge valves to COW line017VCP 027VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenPort and starboard slop tank fixed tank washing machine valves016VTC 040VTC
CloseVary position of No.2 COP isolating valve to top line009VCP
OpenPort slop tank stripping suction valve030VCP
OpenStripping pump suction and discharge valves067VCP 064VCP
OpenMARPOL  line  valves  to  manifold  being discharged from211VCD 219VCD 215VCD if port side or 210VCD 218VCD 214VCD if starboard side

The  automatic  draining  system  should  be  started  up  when the  first  tank  reaches  a 1.5m  sounding.  Drain  the  starboard slop using No.1 COP then change over the pump suction to No.1  COT.  Drain  the  port  slop  tank  then  change  over  the pump suction to No.5 COT. At this point set up the fixed tank cleaning machine at the correct angle (130° to 0°) to COW the port slop tank, taking drive from No.5 COT and draining using the stripping pump via the MARPOL line. Shut in No.2 top line isolating valve to maintain at least 0.8MPa on the COW line if required during the wash.

f) Start the stripping pump and carry out a full COW of the port slop tank. On completion of COW stop the stripping pump and prepare to COW the starboard slop tank using No.1 COP and line. Return No.2 COP to full discharge from No.5 COT.

PositionDescriptionValve
OpenNo.2 COP discharge valves to COW line017VCP 027VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
ClosePort slop tank fixed tank washing machine valves016VTC 040VTC
OpenNo.2 COP isolating valve to top line009VCP
ClosePort slop tank stripping suction030VCP
CloseStripping suction valve064VCP
CloseMARPOL   line  valve   to  manifold   being discharged from215VCD if port side or 214VCD if starboard side

g)     Set up to COW the starboard slop tank taking the drive fluid from No.1 COP and No.1 COT, draining the slop tank with the stripping pump and discharging up the MARPOL line to No.1 manifold. Start the stripping pump

PositionDescriptionValve
OpenNo.1 COP discharge valves to COW line015VCP 016VCP
CloseNo.1 COP isolating valve to top line004VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenStarboard slop tank fixed tank washing machine valves016VTC 039VTC
OpenStarboard slop tank stripping suction valve033VCP
OpenStripping pump suction valve064VCP
OpenStripping pump discharge valves via the MARPOL line to the hose connected to No.1 line port or starboard213VCD if port side or 212VCD if starboard side

h) On completion of COW return No.1 COP to discharging ashore from No.1 COT, stop the stripping pump. Drain the COW and MARPOL lines back to the starboard slop tank then slowly open the main suction to the starboard slop tank, running back from No.1 COT until the tank is 50% full.

PositionDescriptionValve
CloseNo.1 COP discharge valves to COW line015VCP 016VCP
OpenNo.1 COP isolating valve to top line004VCP
OpenStripping pump return valve from discharge to suction side of pump083VCP
OpenCOW line drain valves to starboard slop tank021VCP 031VCP
ClosePump room COW line isolating valves to tank cleaning machines after draining019VCP 201VTC
CloseStarboard slop tank fixed tank washing machine valves016VTC 039VTC
CloseStarboard slop tank stripping suction valve033VCP
CloseStripping pump suction valve064VCP
CloseStripping pump discharge valves via the MARPOL line to the hose connected to No.1 line port or starboard211VCD 219VCD 213VCD if port side or 210VCD 218VCD 212VCD if starboard side
CloseStripping pump return valve from discharge to suction side of pump083VCP
CloseCOW line drain valves to starboard slop tank021VCP 031VCP

i) Set up to run from No.3 COT to port slop tank until the tank is 50% full. Set up to run back from No.1 COT to starboard slop tank until the tank is 50% full.

PositionDescriptionValve
OpenPort slop tank stripping suction valve030VCP
OpenStripping line valves from No.3 line to port slop tank075VCP 062VCP 059VCP
OpenStarboard slop tank main suction valve127VCT

j) On completion of running back continue on full discharge from No.1 COT, No.3 COT and No.5 COT until the next tanks are ready for top washing.

PositionDescriptionValve
OpenPort slop tank stripping suction valve030VCP
OpenStripping line valves from No.3 line to port slop tank075VCP 062VCP 059VCP
OpenStarboard slop tank main suction valve127VCT

k) As No.3 COT approaches the ullage for top COW set up the fixed tank cleaning machines at the correct angle (130° to 70°) ready to COW taking drive fluid from No.3 COT. Close in No.3 top line isolating valve as necessary to maintain 0.8MPa. On completion of top COW continue discharge of No.3
COT starting the automatic draining system when the ullage approaches draining level. Partially drain the tank.

PositionDescriptionValve
OpenNo.3 COP discharge valves to COW line018VCP 028VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.3 COT tank fixed tank washing machine valves012VTC 027VTC 028VTC 029VTC
OpenNo.3 COT stripping suction valves112VCD 114VCD
CloseNo.3 COP isolating valve to top line014VCP
CloseNo.3 COT main suction valves111VCT 113VCT
ClosePump room COW line isolating valves to tank cleaning machines019VCP
CloseNo.3 COP discharge valves to COW line018VCP 028VCP

l)      Now set up and bottom COW No.3 COT using No.3 COP re- cycling on the port slop tank for drive fluid and draining with the eductor.

PositionDescriptionValve
OpenNo.3 COP discharge valves to COW line018VCP 028VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.3 COT tank fixed tank washing machine valves012VTC 027VTC 028VTC 029VTC
CloseNo.3 COP isolating valve to top line014VCP
CloseNo.3 manifold valve205VCD or 206VCD
CloseNo.3 COP suction intermediate block valve012VCP
OpenNo.3 COP suction line to port slop tank036VCP 039VCP 029VCP
OpenNo.3 COP discharge valves to the port slop tank020VCP 022VCP 023VCP 024VCP
OpenEductor suction line to No.3 bottom line063VCP 062VCP 075VCP
OpenNo.3 COT stripping suction valves112VCT 114VCT

m) On completion of COW drain COW line back to the slop tank. Change over No.3 COP to discharging ashore from No.6 COT.

PositionDescriptionValve
CloseNo.3 COP discharge valves to COW line018VCP 028VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.3 COP isolating valve to top line014VCP
CloseNo.3 COT tank fixed tank washing machine valves012VTC 027VTC 028VTC 029VTC
OpenNo.3 manifold valve205VCD or 206VCD
OpenNo.3 COP suction intermediate block valve012VCP
PositionDescriptionValve
CloseNo.3 COP suction line to port slop tank036VCP 039VCP 029VCP
CloseNo.3 COP discharge valves to the port slop tank020VCP 022VCP 023VCP 024VCP
CloseEductor suction line to No.3 bottom line063VCP 062VCP 075VCP
CloseNo.3 COT stripping suction valves112VCT 114VCT
OpenNo.6 COT main suction valves123VCT 125VCT

n)     When No.5 COT reaches the draining level, drain with No.2 COP using the automatic stripping system then change over to discharge from No.2 COT. Discharge No.1 COT to the draining level then set up and COW No.1 COT using No.1 COP, re- cycling on the starboard slop tank for drive fluid and the eductor for draining

Note: During the discharge of No.2 COT adjust the pump speed to ensure that COW of No. 6 COT is completed, and that the discharge of the port slop tank and a transfer of 1,000m3 to port slop tank from No. 2 COT all take place before the draining level is reached in No.2 COT.

PositionDescriptionValve
OpenNo.1 COP discharge valves to COW line015VCP 016VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.1 COT tank fixed tank washing machine valves010VTC 020VTC 021VTC 022VTC
CloseNo.1 COP isolating valve to top line004VCP
CloseNo.1 manifold valve either port or starboard whichever the discharge hose is connected to202VCD or 201VCD
CloseNo.1 COP suction intermediate block valve002VCP
OpenNo.1 COP suction line to starboard slop tank032VCP 034VCP 037VCP
PositionDescriptionValve
OpenNo.1 COP discharge valves to the starboard slop tank020VCP 022VCP 031VCP
OpenEductor suction line to No.1 bottom line063VCP 060VCP 073VCP
OpenNo.1 COT stripping suction valves101VCT 103VCT
CloseNo.5 COT suction valves119VCT 120VCT 121VCT 122VCT
OpenNo.2 COT suction valves105VCT 106VCT 107VCT 108VCT

o)     On completion of COW, drain the COW lines to the starboard slop tank and change over to full discharge from No.4 COT

PositionDescriptionValve
CloseNo.1 COP discharge valves to COW line015VCP 016VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseNo.1 COT tank fixed tank washing machine valves010VTC 020VTC 021VTC 022VTC
OpenNo.1 COP isolating valve to top line004VCP
OpenNo.1 manifold valve either port or starboard whichever the discharge hose is connected to202VCD or 201VCD
OpenNo.1 COP suction intermediate block valve002VCP
CloseNo.1  COP  suction  line  to  starboard  slop tank032VCP 034VCP 037VCP
CloseNo.1 COP discharge valves to the starboard slop tank020VCP 022VCP 031VCP,
CloseEductor suction line to No.1 bottom line063VCP 060VCP 073VCP
PositionDescriptionValve
CloseNo.1 COT stripping suction valves101VCT 103VCT
OpenNo.4 COT main suction valves115VCT 117VCT

p)     Continue discharge of No.6 COT starting the automatic draining system  when  the  ullage  approaches  draining  level.  Partially drain the tank then set up and COW No.6 COT using No.3 COP re-cycling on the port slop tank and draining with the eductor.

PositionDescriptionValve
OpenNo.6 COT stripping suction valves124VCT 126VCT
CloseNo.6 COP main suction valves123VCT 125VCT

q) Carry out a full COW of No.6 COT.

PositionDescriptionValve
OpenNo.3 COP discharge valves to COW line018VCP 028VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.6 COT tank fixed tank washing machine valves015VTC 033VTC 034VTC 035VTC
CloseNo.3 COP isolating valve to top line014VCP
CloseNo.3 manifold valve either port or starboard whichever the discharge hose is connected to206VCD or 205VCD
CloseNo.3 COP suction intermediate block valve012VCP
OpenNo.3 COP suction line to port slop tank036VCP 038VCP 029VCP
OpenNo.3 COP discharge valves to the port slop tank020VCP 022VCP 023VCP 024VCP
OpenEductor suction line to No.3 bottom line063VCP 062VCP 075VCP
PositionDescriptionValve
CloseNo.3 COP discharge valves to COW line018VCP 028VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseNo.6 COT tank washing machines015VTC 033VTC 034VTC 035VTC
OpenNo.3 COP isolating valve to top line014VCP
OpenNo.3 manifold valve either port or starboard whichever the discharge hose is connected to206VCD or 205VCD
OpenNo.3 COP suction intermediate block valve012VCP
CloseNo.3 COP suction line to port slop tank036VCP 038VCP 029VCP
CloseNo.3 COP discharge valves to the port slop tank020VCP 022VCP 023VCP 024VCP
CloseEductor suction line to No.3 bottom line063VCP 062VCP 075VCP

s) Discharge the port slop tank ashore using No.3 COP, then stop No.3 COP and shut down No.3 pump and line. This completes the discharge and COW of Group 3 COTs. Transfer from No.2
COT to the port slop tank until it is 50% full.

PositionDescriptionValve
OpenNo.3 COP suction line to port slop tank using the stripping pump crossover valves075VCP 062VCP 059VCP
OpenPort slop tank stripping suction valve030VCP
CloseNo.3 manifold valve either port or starboard whichever the discharge hose is connected to when discharge of slop tank is complete206VCD or 205VCD
CloseNo.3 COP suction and discharge valves013VCP M03VCP
CloseNo.3 top line isolating and block valves014VCP 265VCP
CloseNo.3 bottom line intermediate and bulkhead master valves011VCP 012VCP
OpenPort slop tank main suction valve slowly128VCP
PositionDescriptionValve
OpenNo.2 COP discharge to the port slop tank018VCP 028VCP 020VCP 022VCP 023VCP 024VCP

t) On completion of transfer, continue discharge of No.2 COT ashore, draining the tanks using the automatic draining system, ready for COW.

PositionDescriptionValve
CloseNo.2 COP discharge valves to COW line018VCP 028VCP
ClosePort slop tank suction valve128VCT

u) Carry out a full COW of No.2 COT using No.2 COP re-cycling on the port slop tank and draining with the eductor followed by a full COW of No.5 COT; redrain No.2 and 5 COT on completion.

PositionDescriptionValve
OpenNo.2 COP discharge vzalves to COW line017VCP 027VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseNo.2 COP isolating valve to top line009VCP
CloseNo.2 manifold valve either port or starboard whichever  the  discharge  hose  is  connected to204VCD or 203VCD
CloseNo.2 COP suction intermediate block valve007VCP
OpenNo.2 COP suction line to port slop tank035VCP 038VCP 029VCP
OpenNo.2 COP discharge valves to the port slop tank via the eductor020VC 022VCP 023VCP 024VCP
OpenEductor suction line to No.2 bottom line063VCP 061VCP 074VCP
OpenNo.2 COT tank fixed tank washing machine valves011VTC 024VTC 025VTC 036VTC
PositionDescriptionValve
OpenNo.5 COT tank fixed tank washing machine valves014VTC 033VTC 034VTC 035VTC
CloseNo.2 COT main suction valves105VCT 107VCT
OpenNo.5 COT stripping suction valves120VCT 122VCT
CloseNo.2 COT stripping suction valves106VCT 108VCT

v) On completion of COW, drain the COW line to the port slop tank then discharge the port slop tank ashore. At the same time set up and carry out a full COW of No.4 COT.

PositionDescriptionValve
CloseNo.2 COP discharge valves to COW line017VCP 027VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.2 COP isolating valve to top line009VCP
OpenNo.2 manifold valve either port or starboard whichever the discharge hose is connected to204VCD or 203VCD
OpenNo.2 COP suction intermediate block valve007VCP
CloseNo.2 COP suction line to port slop tank035VCP 038VCP 029VCP
CloseNo.2 COP discharge valves to the port slop tank via the eductor020VCP 022VCP 023VCP 024VCP,
CloseEductor suction line to No.2 bottom line063VCP 061VCP 074VCP
CloseNo.2 COT tank fixed tank washing machine valves011VTC 024VTC 025VTC 036VTC
CloseNo.5 COT tank fixed tank washing machine valves014VTC 033VTC 034VTC 035VTC
PositionDescriptionValve
CloseNo.5 COT stripping suction valves120VCT 122VCT
CloseNo.2 COT stripping suction valves106VCT 108VCT
OpenPort slop tank suction valve128VCP

w)    When the port slop tank is drained stop No.2 COP and shut down No.2 top and bottom line. This completes the discharge and COW of the Group 2 COTs.

PositionDescriptionValve
CloseNo.2 manifold valves204VCD or 203VCD
ClosePort slop tank suction valve128VCT
CloseNo.2 COP top line isolating valve009VCP
CloseNo.2 top line block valve264VCD
CloseNo.2 COP suction valve008VCP
CloseNo.2 COP discharge valveM02VCP
CloseNo.2 bottom line intermediate block valve007VCP
CloseNo.2 bottom line bulkhead master valve006VCP

x)     Set up and carry out a full COW of No.4 COT using No.1 COP re-cycling  on the starboard  slop tank and draining  using the eductor.

PositionDescriptionValve
OpenNo.1 COP discharge valves to COW line015VCP 016VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseNo.1 COP isolating valve to top line009VCP
CloseNo.1 manifold valve either port or starboard whichever the discharge hose is connected to202VCD or 201VCD
CloseNo.1 COP suction intermediate block valve007VCP
OpenNo.1 COP suction line to starboard slop tank034VCP 037VCP 032VCP
OpenNo.1 COP discharge valves to the starboard slop tank via the eductor020VCP 022VCP 031VCP,
PositionDescriptionValve
OpenEductor suction line to No.1 bottom line063VCP 060VCP 073VCP
OpenNo.4 COT tank fixed tank washing machine valves013VTC 030VTC 031VTC 032VTC
CloseNo.4 COT main suction valves115VCT 117VCT
OpenNo.4 COT stripping suction valves116VCT 118VCT

y) On completion of COW in No.4 COT carry out final draining of No.1 and 4 COT, drain the COW line back to the starboard slop tank then discharge the starboard slop tank ashore.

PositionDescriptionValve
CloseNo.1 COP discharge valves to COW line015VCP 016VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.1 COP isolating valve to top line009VCP
OpenNo.1 manifold valve either port or starboard whichever the discharge hose is connected to202VCD or 201VCD
OpenNo.1 COP suction intermediate block valve007VCP
CloseNo.1 COP suction line to starboard slop tank034VCP 037VCP 032VCP
CloseNo1  COP discharge  valves  to the starboard slop tank via the eductor020VCP 022VCP 031VCP,
CloseEductor suction line to No.1 bottom line063VCP 060VCP 073VCP
CloseNo.4 COT tank fixed tank washing machine valves013VTC 030VTC 031VTC 032VTC
CloseNo.4 COT stripping suction valves116VCT 118VCT
OpenStarboard slop tank suction valve127VCT

z)     Discharge  the  starboard  slop  tank  ashore.  When  the  tank approaches draining level start the automatic stripping system and drain the tank. This now completes the discharge of cargo for the Group 1 tanks. Stop No.1 COP, shut the manifold valve and close all valves on No.1 top and bottom line.

PositionDescriptionValve
CloseNo.1 manifold valves202VCD or 201VCD
CloseStarboard slop tank suction valve127VCT
CloseNo.1 COP top line isolating valve004VCP
CloseNo.1 top line block valve263VCD
CloseNo.1 COP suction valve003VCP
CloseNo.1 COP discharge valveM01VCP
CloseNo.1 bottom line intermediate block valve002VCP
CloseNo.1 bottom line bulkhead master valve001VCP

aa)   It is now necessary to drain lines and pumps using the stripping pump discharging up the MARPOL line to the appropriate shore hose.

bb)   On completion of line draining, close all valves and agree ship/shore figures.

Segregated ballast loading should be started as in the chief officer’s discharging plan, consistent with maintaining the trim and stress within acceptable limits.

PART CARGO DISCHARGE

There are times due to requirements  where  a partial  discharge  of cargo is required. This will only be carried out where all the stress and stability criteria are met.

The partial discharge may consist of one complete parcel of a multigrade cargo or part of a particular grade. Prior to loading, the vessel will be informed of any requirements for part discharge so that the cargo can be loaded in such a manner that the slop tanks are available in order that maximum draining can be achieved using the eductor.

Prior to arrival at the discharge port, a cargo plan shall be completed covering all aspects of the proposed discharging  operation. This will ensure that the stability, stress, draught and trim are all within acceptable levels throughout the discharge, and comply at all times with terminal restrictions.

In addition, the following factors are to be considered and included in the cargo plan prior to the discharge:

•    Maximum available draught at the berth

•    Maximum allowable freeboard on the berth

•    Grade segregation, if carrying multiple grades

•    Crude oil washing requirements

•    Heavy weather ballast requirements

•    Maintenance of satisfactory trim and stress

•    Ballasting operations

Ship/shore  safety  checklists  shall  be  completed  prior  to  starting  cargo discharge, the cargo system lined up and valves double checked.

In this case example the intention is to discharge the group 1 tanks with COW of No.1 and No.4 COT whilst  maintaining  a two valve separation  and no pipeline admixture.

a)   Initially all cargo valves should be shut. The engineering department  should  prepare  the  IG  system,  initilise  the  O2 analyser  and  steam  blow  the  boiler  uptake  valves,  starting and stopping of the IG plant is conducted from the CCR. The engine room staff will also prepare the cargo oil pump turbines and auxiliary systems in order to make the cargo oil pump(s) ready for operation. Set up the cargo system and tanks ready to commence discharge of cargo. The intention is to discharge the starboard slop tank with No.1 COP and line.

PositionDescriptionValve
OpenDeck isolating valve and start IG system902VIG
OpenNo.1 intermediate and bulkhead master valves001VCP 002VCP
OpenNo.1 COP suction valve003VCP
Crack OpenStarboard slop tank suction valve127VCT

b)     Prime the No.1 bottom line and No.1 COPT separator. If using the AUS system gas extration valve to remove the atmosphere inside  the  pipline  and  separator,  ensure  the  line  up  to  the vacuum pumps is not also primed due to the head on the cargo tank. After the separator is fully primed the slop tank suction valve can be fully opened.

PositionDescriptionValve
OpenNo.1 COP discharge valve to top lineM01VCP
OpenNo.1 line top line block valve004VCP

c)     When  the  shore  terminal  confirm  they  are  ready  to  receive cargo, open the manifold valves the lines are connected to, then start No.1 COP.

PositionDescriptionValve
OpenManifold valves that the discharge valves  are connected to202VCD if port side   201VCD if starboard side

d)     Commence the discharge at minimum speed, carrying out all safety and integrity checks after No.1 COP is started, then debottom all group 1 tanks by at least 1m to remove any wet crude.

PositionDescriptionValve
OpenNo.1 COT suction valves101VCT 103VCT
CloseStarboard slop tank suction valve127VCT
OpenNo.4 COT suction valves115VCT 117VCT
CloseNo.1 COT suction valves101VCT 103VCT
OpenStarboard slop tank suction valve127VCT
CloseNo.4 COT suction valves115VCT 117VCT

e)     Once  the  system   has  been  proved,   and  with  the  shore installation’s agreement, increase the pump speed until the maximum permitted back pressure or flow rate is achieved.

e)     As the starboard slop tank approaches the ullage for draining, start the automatic stripping system. On completion of draining the starboard slop tank, open No.1 COT.

PositionDescriptionValve
CloseStarboard slop tank suction valve127VCT
OpenNo.1 COT suction valves101VCT 103VCT

f)     Refill the starboard slop tank with clean cargo to approximately 50% ullage, sufficient to cover the eductor discharge into the tank. Slowly open the slop tank main suction valve and recharge with fresh crude from No.1 COT.

PositionDescriptionValve
OpenSlop tank main suction valve127VCT

g)     On completion of recharging, shut the slop tank main suction valve and increase No.1 COP to maximum rpm. If sufficient ullage has not been attained in the slop tank, additional crude can be transferred  to the starboard  slop tank  via No.1  COP discharge valves through the eductor.

PositionDescriptionValve
CloseStarboard slop tank main suction valve127VCT

h) When No.1 COTs reach the top wash ullage, set up No.1 COP to supply crude from No.4 COT via the COW line to the fixed tank cleaning machines. If pressure cannot be maintained at 0.8MPa whilst washing two tanks then wash one tank at a time. When the top COW is completed return No.1 COP to discharging No.1 COT.

PositionDescriptionValve
OpenNo.1 COP valves to the COW line015VCP 016VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
OpenNo.1 COT tank fixed tank washing machine valves010VTC 020VTC 021VTC 022VTC
PositionDescriptionValve
CloseNo.1 COT main suction valves101VCT 103VCT
OpenNo.4 COT main suction valves115VCT 117VCT
OpenNo.1 COT suction valves101VCT 103VCT
CloseNo.4 COT main suction valves115VCT 117VCT

i) When No.1 COTs reach the draining level, start the automatic draining system, open No.1 COT stripping suction valves and drain both tanks. On completion of draining change over to No.4 COT.

PositionDescriptionValve
CloseNo.1 COP valves to the COW line015VCP 016VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
CloseNo.1 COT tank fixed tank washing machine valves010VTC 020VTC 021VTC 022VTC
OpenNo.1 COT stripping suction valves102VCT 104VCT
CloseNo.1 COT main suction valves101VCT 103VCT
OpenNo.4 COT main suction valves115VCT 117VCT
CloseNo.1 COT stripping suction valves102VCT 104VCT

j) When No.4 COTs reach the draining level, set up the automatic draining system and drain both tanks. Now set up the No.1 COP to re-cycle on the starboard slop tank using the eductor to drain the COT.

PositionDescriptionValve
OpenEductor discharge to starboard slop tank020VCP 022VCP 031VCP
OpenNo.1 COP discharge to the COW line015VCP 016VCP
OpenPump room COW line isolating valves to tank cleaning machines019VCP 201VTC
PositionDescriptionValve
OpenNo.1 and No.4 COTs fixed tank washing machine valves010VTC 020VTC 021VTC 022VTC 013VTC 030VTC 031VTC 032VTC
CloseNo.1 COP isolating valve to top line004VCP
OpenEductor suction valves to No.1 bottom line063VCP 060VCP 073VCP
OpenNo.1 COP suction to port slop tank034VCP 037VDP 032VCP
CloseNo.1 bottom line intermediate block valve002VCP
CloseNo.4 COT main suction valves115VCT 117VCT
CloseNo.1 manifold port or starboard that the shore hose is connected to.202VCD or 201VCD
OpenNo.1 COT stripping suction valves102VCT 104VCT
OpenNo.4 COT stripping suction valve116VCT 118VCT
CloseNo.1 COT stripping suction valves102VCT 104VCT

k)     On  completion  of  COW,  discharge  the  starboard  slop  tank ashore, draining the tank with the automatic draining system.

PositionDescriptionValve
CloseEductor discharge to starboard slop tank020VCP 022VCP 031VCP
CloseNo.1 COP discharge to the COW line015VCP 016VCP
ClosePump room COW line isolating valves to tank cleaning machines019VCP 201VTC
PositionDescriptionValve
CloseNo.1 and No.4 COTs fixed tank washing machine valves010VTC 020VTC 021VTC 022VTC 013VTC 030VTC 031VTC 032VTC
OpenNo.1 COP isolating valve to top line004VCP
CloseEductor suction valves to No.1 bottom line063VCP 060VCP 073VCP
CloseNo.1 COP suction to port slop tank034VCP 037VDP 032VCP
OpenNo.1 bottom line intermediate block valve002VCP
OpenStarboard slop tank suction127VCT
CloseNo.4 COT stripping suction valve116VCT 118VCT

l) When draining is completed stop No.1 COP, shut the manifold valve, port or starboard, that the shore hose is connected to and drain lines as explained before in blog.

PositionDescriptionValve
CloseNo.1 Manifold valves202VCD or 201VCD
CloseStarboard slop tank suction valve127VCT
CloseNo.1 COP top line isolating valve004VCP
CloseNo.1 top line block valve263VCD
CloseNo.1 COP suction valve003VCP
CloseNo.1 COP discharge valveM01VCP
CloseNo.1 bottom line intermediate block valve002VCP
CloseNo.1 bottom line bulkhead master valve001VCP

m) On completion of line draining close all valves and agree ship/shore figures.

Segregated ballast loading should be started as in the chief officer’s discharging plan, consistent with maintaining the trim and stress within acceptable limits.

Leave a Reply

Your email address will not be published. Required fields are marked *